|
|
|
|
|
Contents
2.1.1 Monitoring Requirements and Equipment
2.1.2 Monitoring Schedule for the Reporting Month
2.1.3 Results and Observations
2.2.1 Monitoring Requirements and Equipment
2.2.2 Monitoring Schedule for the Reporting Month
2.2.3 Results and Observations
2.5.1 Preserved Plant Species of Conservation
Importance
2.5.2 Transplanted Plant Species of Conservation
Importance
2.7 Soft Shore Ecological Monitoring
2.10 LANDSCAPE AND VISUAL MONITORING
2.11 IMPLEMENTATION STATUS OF ENVIRONMENTAL MITIGATION MEASURES
2.12 SUMMARY OF COMPLAINTS,
NOTIFICATION OF SUMMONS AND SUCCESSFUL PROSECUTIONS
ANNEX b Environmental
Mitigation Implementation Schedule
ANNEX c Status
of Submissions and Implementation Status of Mitigation Measures under EP
ANNEX d Status
of Statutory Environmental Requiremens
ANNEX e1 Calibration
Certificates for Air Quality
ANNEX e2 Monitoring
Schedule for Air Quality
ANNEX e3 Monitoring
Results for Air Quality
ANNEX e4 Event and
Action Plan for Air Quality
ANNEX f1 Calibration
Certificates for Noise
ANNEX f2 Monitoring
Schedule for Noise
ANNEX f3 Monitoring
Results for Noise
ANNEX f4 Event and
Action Plan for Noise
ANNEX g Compensation
Woodland Monitoring
ANNEX h Preserved/Transplanted
Plant Species of Conservation Importance Monitoring
ANNEX h1 Preserved Plant
Species of Conservation Importance
ANNEX I Eco-shoreline
Monitoring
ANNEX J Landscape
and Visual Monitoring
ANNEX J1 Examples
of Landscape and Visual Mitigation Measures
ANNEX J2 Event and
Action Plan for Landscape and Visual Mitigation Measures
ANNEX L
Monitoring Schedule for the Next Reporting Period
List of Tables
Table 1.1 Contact Information of Key Personnel
Table 1.2 Major Activities in the Reporting Period
Table 1.3 Summary of Status for the Environmental
Aspects under the Updated EM&A Manual
Table 2.1 Action and Limit Levels for 1-hour TSP
Table 2.2 Air Quality Monitoring Details
Table 2.3 Summary of 1-hour TSP Monitoring Results
in the Reporting Period
Table 2.4 Action and Limit Levels for Construction
Noise
Table 2.5 Noise Monitoring Details
Table 2.6 Summary of Construction Noise Monitoring
Results in the Reporting Period
Table 2.7 Key Observations Identified during the
Site Inspection in this Reporting Month
Table 2.8 Quantities of Different Waste Generated
and Imported Fill Materials
Table 2.9 Implementation Status of Landscape and
Visual Mitigation Measures
LIST OF FIGURES |
|
Acronyms
and abreviations
Acronyms |
Description |
C&D |
Construction and Demolition |
CAP |
Contamination Assessment Plan |
CEDD |
Civil Engineering and Development Department |
CWD |
Chinese White Dolphin |
DCM |
Deep Cement Mixing |
DO |
Dissolved Oxygen |
EIA |
Environmental Impact Assessment |
EIAO |
Environmental Impact Assessment Ordinance |
EIS |
Ecologically Important Stream |
EM&A |
Environmental Monitoring and Audit |
EP |
Environmental Permit |
EPD |
Environmental Protection Department |
ER |
Engineer's Representative |
ERM |
ERM-Hong Kong, Limited |
ET |
Environmental Team |
HVS |
High Volume Sampler |
IEC |
Independent Environmental Checker |
PDA |
Planned Development Area |
PME |
Powered Mechanical Equipment |
QPME |
Quality Powered Mechanical Equipment |
RAP |
Remediation Action Plan |
RR |
Remediation Report |
RTTM |
Real Time Tracking and Monitoring |
SS |
Suspended Solid |
TCB |
Tung Chung Bay |
TCE |
Tung Chung East |
TCNTE |
Tung Chung New Town Extension |
TCW |
Tung Chung West |
The Project |
Tung Chung New Town Extension (East) |
THW |
Tai Ho Wan |
TSP |
Total Suspended Particulate |
Updated EM&A Manual |
Updated Environmental Monitoring and Audit Manual for Tung Chung New Town Extension prepared by ERM under Agreement No. CE 60/2017 (EP) and deposited to EPD under Environmental Permit No. EP-519/2016 |
Tung Chung New Town Extension (TCNTE) is one of the major
initiatives under the Government's multi-pronged approach to increase land
supply to meet Hong Kong's medium- to long-term needs for housing, economic and
social developments. The Environmental Impact Assessment (EIA) Report for
TCNTE (Register No. AEIAR-196/2016) was approved on 8 April 2016 and the
Environmental Permit (EP) No. EP-519/2016, covering the construction and
operation of TCNTE, was granted on 9 August 2016. The EIA Report and EP
cover both Tung Chung East (TCE) and Tung Chung West (TCW). ERM-Hong
Kong, Limited (ERM) is commissioned to undertake the role of Environmental Team
(ET) for the construction and operation of TCE Project (“the Project”) in
accordance with the requirements specified in the EP, Updated Environmental
Monitoring and Audit (EM&A) Manual, EIA Report of the TCNTE project and
other relevant statutory requirements.
The construction of the Contract No. NL/2017/03 - Tung Chung New Town Extension – Reclamation and Advance
Works (“Contract 1”) at TCE commenced on 9 July 2018.
The construction of the Contract No. NL/2020/02 - Tung Chung
New Town Extension – Salt Water Supply System
(“Contract 2”) at TCE commenced on 4 September 2021.
The construction of the Contract No. NL/2020/03 - Tung Chung
New Town Extension – Major Infrastructure Works in Tung Chung East (“Contract
3”) at TCE commenced on 5 November 2021.
The construction of the Contract No. NL/2020/07 - Tung Chung
New Town Extension – Tai Ho Interchange (“Contract 7”) at TCE commenced on 15
March 2022.
This is the Monthly EM&A report presenting the EM&A
works carried out during the period from 1 to 31 October 2024 for the TCE
Project in accordance with the Updated EM&A Manual.
A summary of monitoring and audit activities conducted in
the reporting period is listed below:
Air Quality
Monitoring
5 sessions
Noise
Monitoring
5 sessions
Preserved Plant
Species Monitoring
1 session
Environmental Site Inspection
·
Contract
2
5 sessions
·
Contract
3
4 sessions
·
Contract
7
5 sessions
Environmental Management Meeting
·
Contract
2
1 session
·
Contract
3
1 session
·
Contract
7
1 session
Environmental auditing works, including weekly site
inspections of construction works conducted by the ET, audit of implementation
of Complaint Management Plan, Eco-shoreline Implementation Plan, Detailed
Preservation and/or Translocation of Plant Species of Conservation Importance,
Detailed Compensatory Woodland Planting Plan and Waste Management Plan were conducted in the
reporting period. Based on the audit results and the observation for the
reporting period, environmental pollution control and mitigation measures for
the Project were properly implemented.
No exceedance of Action and Limit Levels was recorded for
construction air quality monitoring in the reporting period.
No exceedance of Action/Limit Levels was recorded for
construction noise monitoring in the reporting period.
Water quality monitoring was suspended in the reporting
period.
The construction of vertical eco-shoreline, mangrove
eco-shoreline and rocky eco-shoreline has been substantially completed.
No eco-shoreline monitoring was scheduled
during the reporting period.
There was no notification of summons or prosecution
recorded in the reporting period.
One (1) environmental complaint related to
Contract 3 was received in the reporting period. Investigation was
conducted for the environmental complaint in accordance with the complaint
handling process as stated in the Complaint Management Plan.
There was no reporting change in
the reporting period.
Potential environmental impacts arising from the upcoming
construction activities in the next reporting period of November 2024 are
mainly associated with dust emission, noise from plant operation during normal
working hours and restricted hours, handling and storage of C&D materials
generated from construction activities, efficiency of wastewater and drainage
management and tree protection. The ET will keep track on the
construction works to confirm compliance of environmental requirements and the
proper implementation of all necessary mitigation measures. The ET will
also recommend to the Contractor about the environmental toolbox topics on the
abovementioned key issues for the coming month.
Tung Chung New Town Extension (TCNTE) is one of the major
initiatives under the Government's multi-pronged approach to increase land
supply to meet Hong Kong's medium- to long-term needs for housing, economic and
social developments. The Environmental Impact Assessment (EIA) Report for TCNTE
(Register No. AEIAR-196/2016) was approved on 8 April 2016 and the
Environmental Permit (EP) No. EP-519/2016, covering the construction and
operation of TCNTE, was granted on 9 August 2016. The EIA Report and EP cover both
Tung Chung East (TCE) and Tung Chung West (TCW).
ERM-Hong Kong, Limited (ERM) is commissioned to undertake
the role of Environmental Team (ET) for the construction and operation of TCE
Project (“the Project”) in accordance with the requirements specified in the
EP, Updated Environmental Monitoring and Audit (EM&A) Manual ([1]), EIA Report of the TCNTE project ([2]) and other relevant statutory
requirements.
The TCNTE comprises the
following elements:
(a) TCE Project
1. Reclamation of the seabed by a non-dredged method at
TCE to form a total of about 130 hectares of land;
2. Construction of about 4.9 kilometers
of seawalls, with an eco-shoreline, three drainage box culvert outfalls, three
circulation drains and a seawater intake at TCE;
3. Provision of infrastructure for Tung Chung Area 58,
including construction of a single two-lane road with a footpath and the
associated utility works;
4. Construction of proposed open space;
5. Construction of roads, footpaths, cycle tracks and the
associated junction / road improvement works;
6. Engineering infrastructure works covering drainage,
sewerage, waterworks (including a fresh water service
reservoir, a salt water service reservoir and a salt water pumping station),
common utility tunnels and landscaping works; and
7. Implementation of environmental mitigation measures
and environmental monitoring and audit programme for the works.
(b) TCW Project
1. Site formation works at TCW;
2. Construction of proposed open space;
3. Construction of the River Park
including a visitor centre at TCW; and
4. Construction of sustainable urban drainage systems at TCW.
The locations of Contracts 1, 2, 3 and 7 are shown in Figure 1.1 to 1.4.
The construction and the reclamation related marine works of Contract 1
commenced on 9 and 13 July 2018, respectively. The construction of
Contracts 2, 3 and 7 commenced on 4 September 2021, 5 November 2021 and 15
March 2022, respectively.
This is the Monthly EM&A Report for the TCE Project
which summarises the key findings of the EM&A programme during the reporting period from 1 to 31 October
2024 for the construction works.
The organization structure of
the Project is shown in Annex A.
The key personnel contact names and contact details are summarized in Table
1.1 below.
Table 1.1 Contact
Information of Key Personnel
Party |
Position |
Name |
Telephone |
Environmental Team (ET) (ERM-Hong Kong, Limited) |
ET Leader |
Kelvin So |
3894 9504 |
Deputy ET Leader |
Raymond Chow |
2271 3281 |
|
Independent Environmental Checker (IEC) (Binnies Hong Kong Limited) |
IEC |
Manuel Chua |
3894 9807 |
Deputy IEC |
Edward Lau |
3894 9695 |
|
Contract No. NL/2017/03 - Tung Chung New Town Extension – Reclamation and Advance Works (Contract 1) |
|||
Civil Engineering and Development Department |
Marine Conservation Officer |
Wo King Tai |
3894 9707 |
Engineer’s Representative (ER) (AECOM Asia Company Limited)
|
Principal Resident Engineer |
Frankie Fan |
3894 9603 |
Chief Resident Engineer |
Chris Cheung |
3894 9604 |
|
Resident Engineer |
Victor Chan |
3894 9666 |
|
Inspector of Works |
Clement Fan |
3894 9798 |
|
Contractor (Build King – SCT Joint Venture)
|
Site Agent |
David Wong |
9653 8635 |
Civil Division Head |
Marco Chan |
9257 7033 |
|
Environmental Officer |
Issac Wong |
9873 8968 |
|
24-hour Complaint Hotline |
- |
5976 1853 |
|
Contract No. NL/2020/02 - Tung Chung New Town Extension – Salt Water Supply System (Contract 2) |
|||
Civil Engineering and Development Department |
Senior Engineer |
Patrick C Y Yeung |
2231 4435 |
Electrical & Mechanical Engineer |
Samson K L Yip |
2231 4460 |
|
Engineer’s Representative (ER) (AECOM Asia Company Limited)
|
Principal Resident Engineer |
Frankie Fan |
3894 9603 |
Senior Resident Engineer |
Sunny Ng |
3894 9605 |
|
Senior Resident Engineer |
Vincent Leung |
3894 9645 |
|
Resident Engineer |
Amen Fung |
3894 9676 |
|
Senior Inspector of Works |
Lai Kwok Wai |
3894 9731 |
|
Contractor (China Geo-Engineering Corporation)
|
Construction Manager |
Ambrose Kwong |
6198 7787 |
Site Agent |
Edward Mok |
6498 4306 |
|
Construction Team Leader |
C K Chung |
5401 5720 |
|
Environmental Officer |
Fung Ka Bao |
9120 1489 |
|
24-hour Complaint Hotline |
- |
5976 1853 |
|
Contract No. NL/2020/03 - Tung Chung New Town Extension – Major Infrastructure Works in Tung Chung East (Contract 3) |
|||
Civil Engineering and Development Department
|
Senior Engineer |
Eddie W C Lam |
2231 4445 |
Senior Engineer |
Phoebe Tang |
2231 4423 |
|
Engineer |
Timothy H M Chan |
2231 4473 |
|
Engineer |
Colin K C Wong |
2231 4417 |
|
Engineer |
Wing Chen |
3894 9704 |
|
Engineer’s Representative (ER) (AECOM Asia Company Limited)
|
Principal Resident Engineer |
Frankie Fan |
3894 9603 |
Chief Resident Engineer |
Gloria Tang |
3894 9639 |
|
Senior Resident Engineer |
Winston Wong |
3894 9650 |
|
Resident Engineer |
Alvis Li |
3894 9558 |
|
Resident Engineer |
Anson Yip |
3894 9559 |
|
Senior Inspector of Works |
Douglas Ng |
3894 9737 |
|
Contractor (Build King Civil Engineering Limited)
|
Construction Manager |
Cheung Siu Lun |
2272 3680 |
Site Agent |
Aldous Lo |
9225 0368 |
|
Deputy Site Agent |
Keith Chau |
9646 8283 |
|
Construction Team Leader |
Kwong Po Hang |
9283 6844 |
|
Environmental Officer |
Tim Lin |
6390 0018 |
|
24-hour Complaint Hotline |
- |
5976 1853 |
|
Contract No. NL/2020/07 - Tung Chung New Town Extension – Tai Ho Interchange (Contract 7) |
|||
Civil Engineering and Development Department |
Senior Engineer |
Phoebe Tang |
2231 4423 |
Engineer |
S H Leung |
2231 4449 |
|
Engineer’s Representative (ER) (AECOM Asia Company Limited) |
Principal Resident Engineer |
Frankie Fan |
3894 9603 |
Senior Resident Engineer |
Kelvin Kwan |
3894 9641 |
|
Senior Resident Engineer |
Brian Li |
3894 9556 |
|
Resident Engineer |
Kingsley Ho |
3894 9552 |
|
Resident Engineer |
Jessie Tang |
3894 9678 |
|
Senior Inspector of Works |
C K Liu |
3894 9733 |
|
Contractor (Build King Civil Engineering Limited) |
Site Agent |
Hon Yee |
9090 3109 |
Deputy Site Agent |
Vincent Kwan |
9833 1313 |
|
Construction Team Leader |
Vincent Lo |
9883 9229 |
|
Environmental Officer |
Nash Wong |
9810 1946 |
|
24-hour Complaint Hotline |
- |
5976 1853 |
As informed by the Contractor,
details of the major works carried out in this reporting period are listed
below:
Table 1.2
Major Activities in the Reporting Period
Activities |
Key Issues |
Key Mitigation Measures |
Contract No. NL/2017/03 - Tung Chung New Town Extension – Reclamation and Advance Works (Contract 1) |
||
Land-based Works |
||
· Removal of siltation at IORC
|
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management · Potential surface runoff · Noise from plant operation during normal working hours or restricted hours · Dust emission during storage and transfer of sand/ sorted public fill |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management · Strictly follow requirement under CNP for the use of PMEs and works within restricted period · Use of acoustic mat and other noise mitigation measures when necessary · Regular maintenance of engines and mechanical equipment |
Contract No. NL/2020/02 - Tung Chung New Town Extension – Salt Water Supply System (Contract 2) |
||
Land-based Works |
||
· Construction of pumping station at Portion 6 · Construction of Intake Culvert at Portion 6 · Construction of service reservoir, TMF mainlaying at Portion 3 · Construction of HDD works at Portion 3 · Watermain laying works at Portion 3 along Man Tung Road, Tung Chung Road and Tung Chung Waterfront Road · Watermain laying works at Yi Tung Road at Portion 4 · Drainage and Sewerage works at Portion 5 · Construction of T-Junction in Yi Tung Road at Portion 5
|
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management · Tree protection |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management · Retain and protect all existing trees and vegetation within the study area which are not directly affected by the works |
Contract No. NL/2020/03 - Tung Chung New Town Extension – Major Infrastructure Works in Tung Chung East (Contract 3) |
||
Land-based Works |
||
· Excavation and ELS works at Portion 104 · Excavation and ELS works at CUT no.1, 2, 3, 4 and supporting building · Construction works for CUT no. 1 structure · Back-filling works for CUT 2 · Construction works and furniture installation of PM office at WA9 · Construction works of Contractor office at WA6 · Drainage, Sewerage and watermain works at Road L4, L3, L5 and Portion 16 · DCS works at Road L4 and L3. · Pipe laying works for twin rising mains/ watermain laying at Man Tung Road · Preparation and pipe jacking works at Ying Tung Road · Pipe jacking works at Yi Tung Road · Foundation and backfilling works for noise barrier at Portion 11 · Road and drainage works in Road P1 · Road widening works at Ying Hei Road · Road D4, Road L7, ELS installation
|
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management
|
Contract No. NL/2020/07 - Tung Chung New Town Extension – Tai Ho Interchange (Contract 7) |
||
Land-based Works |
||
· Open cut excavation, backfilling and pipe laying for rising main and watermain at Portion 146-1 to 146-5 · Pak Mong bridge I-beam erection, insitu construction of abutment and diaphragm and cable trough · Trench excavation and pipe laying works at Portions 32 (Sham Shui Kok Drive) · Trench excavation and pipe laying works at Portion 32 (Access Road adjacent to MTRC Siu Ho Wan Depot) · Establishment of pipe jacking works at Portion 33 · Horizontal grouting at Receiving pit at Portion 32 · RC construction of Retaining Wall FR1 · Pak Mong Subway Extension Phase 2 - preparation works for Demolition · Preparation works for falsework at casting yard A1 and A2 · ELS at A1a, A1b, A2a and A2b · RC for RW-R2 and RW-R4 at Portion 146-2 to 146-4 · RC construction at RW-R7 at Portion 31 · RC works at Wall E · Mini-piles at Wall D · Bored piles at Bridge C at Portion 146-12 · U channel and chain link fence construction at Portion 147-1 and 147-2 · Sign gantry ELS, RC works, crossroad ducts, temporary lighting arrangement and removal of central divider along NLH fast lane · Drainages works at 146-4, 146-6 and 146-7 · Site clearance and tidiness
|
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management · Tree protection |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management · Retain and protect all existing trees and vegetation within the study area which are not directly affected by the works |
The environmental mitigation implementation schedule is
presented in Annex B.
The status for all environmental
aspects is presented in Table 1.3. The EM&A requirements
remained unchanged during the reporting period.
Table 1.3
Summary of Status for the Environmental Aspects under the Updated
EM&A Manual
Parameters |
Status |
|
Air Quality |
||
Baseline Monitoring |
The results of baseline air quality monitoring for TCE were reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4 |
|
Impact Monitoring |
On-going for TCE, monitoring conducted three times every six days |
|
Noise |
|
|
Baseline Monitoring |
The results of baseline noise monitoring for TCE were reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4 |
|
Impact Monitoring |
On-going for TCE, monitoring conducted once per week |
|
Impact Monitoring for Road Traffic Noise during Operational Phase |
To be conducted during operational phase |
|
Fixed Noise Commissioning Test |
To be implemented by the Contractor before operation of TCNTE |
|
Water Quality |
|
|
Baseline Monitoring |
The results of baseline water quality monitoring for TCE were reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4 |
|
Impact Monitoring |
Suspended for TCE with approval from EPD |
|
Waste Management |
|
|
Waste Monitoring |
On-going |
|
Land Contamination |
|
|
Contamination Assessment Plan (CAP), Remediation Action Plan (RAP) and Remediation Report (RR) |
To be conducted under TCW. Refer to the EM&A Reports of TCW. |
|
Ecology |
|
|
Monitoring for Compensation Woodland
|
Compensation Woodland Planting was completed on 30 September 2022 On-going, monitoring conducted quarterly |
|
Monitoring for Emergent Plant inside the future River Park |
To be conducted under TCW. Refer to the EM&A Reports of TCW. |
|
Monitoring for Translocated Amphibians of Conservation Importance |
To be conducted under TCW. Refer to the EM&A Reports of TCW. |
|
Monitoring for Preserved/Transplanted Plant Species of Conservation Importance
|
On-going, for preserved plant species, monitoring conducted once per month; for transplanted plant species, replacement planting was carried out on 28 April 2023 and 19 September 2023. Monitoring conducted once per month for the first year, and quarterly for the second year. |
|
Monitoring for Tung Chung Stream EIS and Wong Lung Hang EIS
|
To be conducted under TCW. Refer to the EM&A Reports of TCW. Monitoring for Wong Lung Hang was not required and the proposal was accepted by EPD on 2 September 2021 |
|
Eco-shoreline Monitoring |
The dry season monitoring between December 2023 and February 2024 was completed. Wet season monitoring between May 2024 and August 2024 was completed. |
|
Tung Chung Bay and Tai Ho Wan Baseline Monitoring |
The results of baseline soft shore ecological monitoring at Tung Chung Bay and Tai Ho Wan were reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4 |
|
Tung Chung Bay and Tai Ho Wan Impact Monitoring |
Completed |
|
Tung Chung Bay and Tai Ho Wan Post-construction Monitoring |
On-going for TCE, monitoring conducted quarterly |
|
Landscape and Visual |
|
|
Baseline Monitoring |
The results of baseline landscape and visual monitoring were reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4 |
|
Impact Monitoring |
On-going |
|
Site Environmental Audit |
|
|
Regular Site Inspection |
On-going |
|
Dolphin Watching Plan implementation measures |
Completed |
|
Works Vessel Travel Route Plan implementation measures |
Completed |
|
Silt Curtain Deployment Plan implementation measures |
All silt curtain was removed in accordance with the Silt Curtain Deployment Plan and after obtaining the acceptance from EPD |
|
Spill Response Plan implementation measures |
Completed |
|
Detailed Preservation and/or Translocation Plan for Plant Species of Conservation Importance implementation measures |
Under implementation by the Contractor of Contract 2 |
|
Detailed Compensatory Woodland Planting Plan implementation measures |
Under implementation by the Contractor of Contract 2 |
|
Waste Management Plan implementation measures |
Under implementation by the Contractor of Contract 1, 2, 3 and 7 |
|
Complaint Hotline and Email Channel |
Under implementation by the Contractor of Contract 1, 2, 3 and 7 |
|
Environmental Log Book |
On-going |
|
Taking into account the construction
works, impact monitoring of air quality, noise and waste management were
carried out in the reporting period. The monitoring schedule of air
quality and noise are provided in Annex E2 and Annex F2 respectively.
The EM&A programme
also involved environmental site inspections and related auditing conducted by
the ET for checking the implementation of the required environmental mitigation
measures recommended in the approved EIA Report and relevant EP submissions,
including Complaint Management Plan, Eco-shoreline Implementation Plan,
Detailed Preservation and/or Translocation Plan for Plant Species of
Conservation Importance, Detailed Compensatory Woodland Planting Plan and Waste
Management Plan.
To promote the environmental
awareness and enhance the environmental performance of the contractors,
environmental trainings and regular environmental management meetings were
conducted during the reporting period, which are summarized as below:
•
Three (3) environmental management committee meetings were held among
the relevant contractors, ER, ET, IEC and CEDD on 8 October 2024 (for Contracts
7) and 16 October 2024 (for Contracts 2 and 3);
•
Environmental toolbox trainings on site clearance, construction dust and
suppression on 8 and 22 October 2024 were conducted for Contract 2;
•
Environmental toolbox trainings on environmental abatement facilities,
acoustic decoupling measures, plant and machinery environmental precaution,
energy saving, site tideness for anti-mosquitos, tree
protection, construction dust and suppression, anti-mosquitos control measures,
chemical waste and handling of chemical spillage on 3, 8, 10, 15, 17, 22, 24 , 29 and 31 October 2024 were conducted for Contract 3;
•
Environmental toolbox trainings on loading, unloading and transfer of
material, stockpiling, backfilling, deposition and compaction of fill material,
scaffolding, rock bolts, rock dowels, soil nail on 2, 9, 16, 23 and 30 October
2024 were conducted for Contract 7.
The status of statutory
environmental compliance with the EP conditions under the EIAO, submission
status under the EP and implementation status of mitigation measures are
presented in Annex C.
The environmental licenses and
permits, including environmental permit, discharge license under Water
Pollution Control Ordinance, registration as chemical waste producer,
construction noise permit and specified processes license, which were valid in
the reporting period are presented in Annex D. No non-compliance with environmental
statutory requirements was recorded.
According to the Updated EM&A
Manual of the Project, impact air quality monitoring in terms of 1-hour Total
Suspended Particulate (TSP) was conducted three (3) times every six (6) days
when the highest dust impact was expected. The Action and Limit Levels of
the air quality monitoring is provided in Table 2.1 below.
Table 2.1
Action and Limit Levels for 1-hour TSP
Location |
Action Level (µg/m3) |
Limit Level (µg/m3) |
Monitoring station for Tung Chung East |
279 |
500 |
Portable direct reading dust meters were used to measure
1-hour TSP levels in undertaking the air quality monitoring for the
Project. The proposed use of portable direct reading dust meters was
submitted to IEC and obtained agreement from the IEC as stated in Section 5.5
of the Updated EM&A Manual. With the use of direct reading dust
meter, it can allow prompt and direct results for the EM&A reporting and
the implementation of the event and action plan. The portable direct reading
dust meter would be calibrated every year against High Volume Sampler (HVS) to
check the validity and accuracy of the results measured by direct reading
method.
The monitoring location and
equipment used in the impact air quality monitoring programme
are summarized in Table 2.2 and illustrated in Figure 2.1. Copies of
the calibration certificates for the equipment are presented in Annex E1, which showed that
the portable direct reading dust meter is capable of providing comparable
results with that provided by a HVS.
Table 2.2
Air Quality Monitoring Details
Monitoring Station |
Location |
Parameter |
Frequency and Duration |
Monitoring Dates |
Equipment |
DM-1 |
Tung Chung Area 56 – Ying Tung Estate |
1-hour TSP |
Three times per six days during the construction period of the Project |
5, 10, 16, 22 and 28 October 2024 |
1-hour TSP Dust Meter SIBATA LD-3B (S/N: 436553, 436560) |
Note: It should be noted that impact
monitoring at other construction dust monitoring locations at TCE as stated in
the Updated EM&A Manual will commence after the flat intake (for Monitoring
Stations DM-2, DM-3 and DM-4).
The schedule for air quality
monitoring during the reporting period is provided in Annex E2.
The monitoring results for
1-hour TSP are summarized in Table 2.3. The monitoring data and
the graphical presentation are provided in Annex E3.
Table 2.3
Summary of 1-hour TSP Monitoring Results in the Reporting Period
Monitoring Station |
Average (µg/m3) |
Range (µg/m3) |
Action Level (µg/m3) |
Limit Level (µg/m3) |
DM-1 |
47 |
35-60 |
279 |
500 |
Major dust sources in the reporting period included haul road
traffic and excavation under the Project.
No exceedance of Action and
Limit Levels was recorded for construction air quality monitoring in the
reporting period. No action was thus required to be undertaken in
accordance with the Event and Action Plan presented in Annex E4.
According to the Updated
EM&A Manual of the Project, impact noise monitoring was conducted once per
week during the construction phase of the Project. The Action and Limit
Level for construction noise of the Project is provided in Table 2.4
below.
Table 2.4
Action and Limit Levels for Construction Noise
Time Period |
Action Level |
Limit Level |
0700 - 1900 hours on normal weekdays |
When one documented complaint is received |
75 dB(A) a, b |
Note:
a Limit level is
exceeded when Leq ≥ 75 dB(A). If works
are to be carried out during restricted hours, the conditions stipulated in the
construction noise permit issued by the Noise Control Authority have to be followed.
b
Reduce to 70 dB
(A) for schools and 65 dB (A) during school examination periods.
Noise monitoring was performed using sound level meter
at the designated monitoring stations NMS-CA-1A ([3]) ([4])
and NMS-CA-4 (Figure 2.2;
Table 2.5) in accordance with the requirements stipulated in the Updated EM&A Manual. Acoustic calibrator
was deployed to check the sound level meters at a known sound pressure
level. Details of the deployed equipment are provided in Table 2.5.
Copies of the calibration certificates for the equipment are presented in Annex F1.
Table 2.5 Noise
Monitoring Details
Monitoring Station a |
Location |
Parameter |
Frequency and Duration |
Monitoring Dates |
Equipment |
NMS-CA-1A b |
Residential premise in Tung Chung East – Century Link/Ying Hong Road c |
30-minute measurement between 0700 and 1900 on normal weekdays (Monday to Saturday). Leq, L10 and L90 would be recorded. |
Once per week for 30 mins during the construction period of the Project |
5, 10, 16, 22 and 28 October 2024 |
Sound Level Meter: Rion NL-52 (S/N: 00331805)
Acoustic Calibrator: LARSON DAVIS CAL200 (S/N: 16172) |
NMS-CA-4 |
Residential premise in the reclamation area next to Tung Chung East – Ying Tung Estate |
Note:
a It should be noted
that impact monitoring at other construction noise monitoring locations at TCE
as stated in the Updated EM&A Manual will commence after the flat intake of
residential premise in TCE (for Monitoring Station NMS-CA-1) and operation of
schools (for Monitoring Stations NMS-CA-2 and NMS-CA-3).
b Impact monitoring at
monitoring station NMS-CA-1A commenced on 19 September 2018 in view of the
close vicinity of the construction works near the residential area at Century
Link.
c Due to land
handover issue, NMS-CA-1A was relocated to Ying Hong Road which is located 60m
away from the original location. Proposal on the relocation of NMS-CA-1A
was approved by IEC on 23 November 2018. Noise monitoring at the
relocated location commenced since 24 November 2018.
The schedule for noise
monitoring during the reporting period is provided in Annex F2.
Results for noise monitoring are
summarized in Table 2.6. The monitoring data and the graphical
presentation are provided in Annex
F3.
Table 2.6 Summary of Construction Noise Monitoring Results
in the Reporting Period
Monitoring Station |
Average, dB(A), |
Range, dB(A), Leq (30mins) |
Limit Level, dB(A), Leq (30mins) |
NMS-CA-1A |
67.4 |
64.7-69.4 |
75 |
NMS-CA-4 |
66.7 |
65.5-68.8 |
75 |
Major noise sources during the noise monitoring included noise
from plant operation, craning, piling, haul road traffic, nearby traffic and
aircraft as well as nearby construction sites.
No Action/Limit Level
exceedance was recorded for construction noise monitoring in the reporting
period. No action was thus required to be undertaken in accordance with
the Event and Action Plan presented in Annex F4.
No monitoring event for impact
water quality monitoring was conducted at all designated monitoring
stations during the reporting period. Water quality monitoring has been
suspended since 3 October 2023 as all reclamation works and marine construction
activities have been completed.
Compensation woodland planting under Contract 2 was
completed on 30 September 2022. With the approval from EPD on the
monitoring proposal in August 2023, quarterly
post-planting monitoring for compensation woodland was commenced in September
2023. No compensation woodland monitoring was carried out in
the reporting month. Photographic record of the compensation woodland
planting is provided in Annex G.
Plant species of conservation
importance, including three individuals of Aquilaria sinensis and 33
individuals of Gmelina chinensis, were identified within works areas for
Contract 2 during the survey conducted in August 2021. All individuals of
Aquilaria sinensis and 31 individuals of Gmelina chinensis were recommended being preserved in-situ while
two individuals of Gmelina chinensis (RT-07 and RT-08) were recommended
being transplanted to the receptor site in accordance with the Detailed
Preservation and/or Translocation Plan for Plant Species of Conservation
Importance approved under Condition 2.21 of EP-519/2016.
Initial tree survey was
conducted in September 2021 under Contract No. NL/2020/02 before the
commencement of construction works. According to the initial tree survey
conducted, the in-situ preserved plant species of conservation
importance of which one individual of Aquilaria sinensis and six
individuals of Gmelina chinensis were found missing.
During the monthly monitoring of the in-situ
preserved plant species of conservation importance in November 2023, one
individual of Aquilaria sinensis and one individual of Enkianthus quinqueflorus
were newly observed and recommended being preserved in-situ.
Registration and measurement for two additional trees were conducted on 4
December 2023.
Monthly monitoring of the in-situ
preserved plant species of conservation importance by the Qualified Personnel
(QP) appointed under Contract 2 was implemented in the reporting period. Health
condition was considered fair for the majority of the in-situ
preserved plant species of conservation importance, of which two individuals of
Gmelina chinensis could not be monitored as a result of unsafe access to
the locations, as recorded during the monitoring carried out on 14 October
2024.
Tree protection zones for the in-situ
preserved plant species of conservation importance were demarcated. No
injuries and/or damages to the individuals of the in-situ preserved
plant species of conservation importance were reported by the QP since the
previous monitoring events. Photographic record and tree schedule of the
preserved plant species of conservation importance monitoring are provided in Annex H1.
The ET will continue to monitor
the implementation of monitoring of in-situ preserved plant species of
conservation importance.
Site visit to the receptor site
for the transplanted plant species of conservation importance under Contract 2
was carried out on 20 January 2022 prior to the commencement of transplantation
works for the transplanted plant species of conservation importance on 21
January 2022.
The transplanted plant species
of conservation importance were both certified as dead trees by the QP on 15
June 2022 as no living signs were observed. Replacement planting of new
trees of the same species, or other species to the satisfaction of the Project
Manager, at the Contractors’ expense would be deemed necessary in accordance
with the conditions under the approved Detailed Preservation and/or
Translocation Plan for Plant Species of Conservation Importance.
Replacement planting of three (3) Aquilaria sinensis were completed on
28 April 2023. One (1) individual was certified dead by the QP as no
living signs were observed on 26 July 2023. The removal of the dead tree
and replanting of one (1) individual of Aquilaria sinensis were
completed on 19 September 2023.
The establishment period of two
(2) individuals of Aquilaria sinensis was ended
on 27 April 2024 and one (1) individual of Aquilaria sinensis was
ended on 18 September 2024.
No transplanted plant species of
conservation importance monitoring was scheduled during the reporting
period.
The transplanted plant species
of conservation importance were watered twice a week during the establishment
period to keep the soil moist except in days with heavy rainfall. The ET
will continue to monitor the implementation of monitoring of in-situ preserved/
transplanted plant species of conservation importance.
The construction of vertical eco-shoreline,
mangrove eco-shoreline and rocky eco-shoreline has been substantially
completed. Photographic record is provided in Annex I.
No eco-shoreline monitoring was scheduled during the
reporting period. Monitoring is conducted for at least 3 years
after the completion of eco-shoreline, twice in wet season and twice in dry
season, while ichthyoplankton and juvenile fish monitoring will be conducted on a monthly basis covering May to August for at least 3
years, in order to determine the effectiveness of the eco-shoreline in
accordance with the Updated EM&A Manual and Eco-shoreline Implementation
Plan.
No post-construction soft shore ecological monitoring at
Tung Chung Bay and Tai Ho Wan was scheduled during the reporting period.
The post-construction soft shore ecological monitoring at Tung Chung Bay and
Tai Ho Wan was scheduled to be conducted in December 2024 in accordance with
the Updated EM&A Manual.
Site inspections were carried
out on a weekly basis with the Contractor and ER to monitor the implementation
of proper environmental pollution control and mitigation measures for air
quality, noise, water quality, waste management, marine ecology, landscape and
visual impacts and preservation and/or transplantation of plant species of
conservation importance under the Project. In the reporting period, five
(5) site inspections were carried out on 3, 9, 16, 23 and 30 October 2024 for
Contract 2, four (4) site inspections were carried out on 4, 10, 16 and 25
October 2024 for Contract 3 and five (5) site inspections were carried out on
3, 8, 15, 22 and 29 October 2024 for Contract 7.
Key observations during the site
inspections are summarized in Table 2.7.
Table 2.7 Key
Observations Identified during the Site Inspection in this Reporting Month
Contract No. |
Inspection Date |
Environmental Observations |
Recommendations/ Remarks |
Contract 2 |
3 October 2024 |
Portion 3 • Insufficient drainage control was observed.
• Wastewater treatment system facility was not properly set up. |
Portion 3 • The Contractor was urged to further improve the drainage / water divert system to prevent runoff.
• The Contractor was urged to rectify immediately and comply with the the discharge licence. |
9 October 2024 |
Portion 6 • Exposed stockpile was observed.
• Dusty haul road was observed. |
Portion 6 • The Contractor was reminded to properly cover up the exposed stockpile.
• The Contractor was reminded to provide adequate dust mitigation measures, such as watering.
|
|
16 October 2024 |
Portion 3 • Exposed stockpile was observed.
Portion 6 • Chemical containers were observed placing on the ground.
|
Portion 3 • The Contractor was reminded to properly cover up the exposed stockpile.
Portion 6 • Contractor was reminded to provide drip tray for chemicals.
|
|
23 October 2024 |
Portion 3, TTA • No deficiency was observed.
|
• Nil.
|
|
30 October 2024 |
Porton 3 • Chemical container was observed placing on the ground. |
Porton 3 • Contractor was reminded to provide drip tray for chemicals. |
|
Contract 3 |
4 October 2024 |
Portion 10, 16b, 104, TTA • No deficiency was observed. |
• Nil. |
10 October 2024 |
Portion 10 • Poor housekeeping was observed.
|
Portion 10 • The Contractor was reminded to maintain good housekeeping.
|
|
16 October 2024 |
TTA • Malfunction of wastewater treatment system tank was observed.
Near Portion 104 • Dust trail was observed on public road.
Main Haul Roads • Dusty haul roads were observed. |
TTA • The Contractor was urged to rectify immediately and ensure wastewater would be properly treated before discharge.
Near Portion 104 • The Contractor was reminded to keep the public road clean and make sure vehicles are properly washed before leaving the site.
Main Haul Roads • The Contractor was urged to provide adequate dust mitigation measures, such as watering. |
|
Portion 104, TTA • Oil stain was observed on ground. |
Portion 104, TTA • The Contractor was urged to clean the oil stain and rectify the situation immediately. |
||
Contract 7 |
3 October 2024 |
Portion 31, 146 • No deficiency was observed. |
• Nil. |
8 October 2024 |
Portion 31, 33 • Appropriate Non-road Mobile Machinery (NRMM) labels were not observed on generator and excavator. |
Portion 31, 33 • The Contractor was reminded to affix appropriate NRMM labels in accordance with the Air Pollution Control (Non-road Mobile Machinery) (Emission) Regulation. |
|
15 October 2024 |
Portion 146 • Chemical containers were observed placing on the ground. |
Portion 146 • The Contractor was reminded to place the chemical containers in drip tray. |
|
22 October 2024 |
Portion 31 • No deficiency was observed. |
• Nil. |
|
29 October 2024 |
Portion 32 • Oil drums were observed placing on the ground.
• Oil stain was observed on ground. |
Portion 32 • The Contractor was reminded to place the oil drums in drip tray.
• The Contractor was urged to clean the oil stain and rectify the situation immediately. |
The Contractors have rectified all of the observations identified during environmental site
inspections in the reporting period. The
Contractors were reminded to implement all relevant mitigation measures related
to construction dust, construction noise, water quality and waste management
outlined in the EIA Report and Updated EM&A Manual.
The Contractors of Contract 1, 2, 3 and 7 have registered as
chemical waste producer. Sufficient numbers of
receptacles were available for general refuse collection and sorting.
All dump trucks engaged on site was equipped with RTTM
system during the reporting period. The Surveillance Team of the ET
conducted regular site inspection on the dump trucks and their track
records. No illegal dumping and landfilling of C&D materials was
found during the reporting period.
Wastes generated during this reporting period include
mainly non-inert construction wastes. Reference has been made to the
waste flow tables prepared by the Contractors. The quantities of
different types of wastes and imported fill materials are summarised
in Table 2.8.
Table 2.8
Quantities of Different Waste Generated and Imported Fill Materials
Contract No. |
Month/ Year |
Inert C&D Materials a (m3) |
Imported Fill b (sand) (m3) |
Imported Fill c (public fill) (m3) |
Inert Construction Waste Re-used d (m3) |
Non-inert Construction Waste e (m3) |
Recyclable Materials f (kg) |
Chemical Wastes (kg) |
TCNTE (East) |
1 to 31 Aug 24 |
0.0 |
0.0 |
0.0 |
5,160.4 |
656.7 |
0.0 |
0.0 |
1 to 31 Sep 24 |
0.0 |
0.0 |
0.0 |
28,512.0 |
628.9 |
0.0 |
0.0 |
|
1 to 31 Oct 24 |
0.0 |
0.0 |
0.0 |
17,042.0 |
295.0 |
364.0 |
1,600.0 |
Note:
a Inert construction wastes
include hard rock and large broken concrete, and materials disposed as public
fill.
b
Imported materials
include of sand fill from any source outside of TCNTE.
c Imported sorted public fill
include all G200, G400 and glass gullet (local recycling materials) from any
source outside of TCNTE.
d Reuse of inert construction
waste generated under the TCNTE contracts.
e Non-inert
construction wastes include general refuse disposed at landfill.
f Recyclable materials
include metals, paper, cardboard, plastics and others.
Implementation of applicable landscape and visual mitigation
measures was monitored in accordance with the Updated EM&A Manual.
All measures undertaken by the Contractor during the construction phase and
establishment work phase shall be audited by ET to ensure compliance with the
intended aims of the measures.
The implementation status of the environmental protection
measures is summarized below in Table 2.9. Examples of landscape
and visual mitigation measures are presented in Annex J1. The monitoring programme
for detailed design, construction and establishment stages is presented in Table
2.10. Event and Action Plan for Landscape and Visual impacts is
stated in Annex J2.
Table 2.9
Implementation Status of Landscape and Visual Mitigation Measures
Landscape and Visual Mitigation Measures during Construction |
Implementation Status |
Relevant Contract(s) in the Reporting Period |
MM1 – Optimization of Construction Areas & Providing Temporary Landscape on Temporary Construction |
Implementation of the measures were carried out during the detailed design stage of the Project. |
NA
|
MM2 – Minimize Topographical Changes |
Implementation of the measures were carried out during the detailed design stage of the Project. |
NA |
MM3 – Preservation of Potentially Registerable OVTs, Rare and Protective Vegetation |
Tree Protection Specifications were provided in the relevant Contract Specifications respectively for implementation by the Contractors under the Project. The Contractors submitted Detailed Preservation and/or Translocation Plan for Plant Species of Conservation Importance under EP condition 2.21. The Contractors’ performance on the implementation of the tree maintenance and protection measures were observed and checked by the ET weekly during construction period. |
All works contracts |
MM4 – Transplanting of Existing Trees
|
Tree Transplanting Specifications were provided in the relevant Contract Specifications respectively for implementation by the Contractors under the Project where trees would unavoidably be affected by the construction works. The Contractors submitted Detailed Preservation and/or Translocation Plan for Plant Species of Conservation Importance under EP condition 2.21. The transplanted plant species of conservation importance were both certified as dead trees by the QP on 15 June 2022 as no living signs were observed. |
Contract 2 |
MM5 – Screen Hoarding
|
All works contracts |
|
MM6 – Adopting Non-dredge Method for the Reclamation |
Not applicable during the reporting period. |
NA |
MM9 – Providing Natural Rock Material/ Planting for Artificial Seawall |
Rock armour reused and construction of eco-shoreline (mangrove eco-shoreline, rocky eco-shoreline and vertical eco-shoreline) in progress. The implementation of mitigation measures was checked by ET during weekly site inspection. Implementation of the measures by Contractors was observed. |
Contract 1 |
MM10 – Compensatory Planting |
Not applicable during the reporting period. |
NA |
MM11 – Woodland Restoration |
The implementation of mitigation measures was checked by ET during weekly site inspection. Implementation of the measures by Contractors was observed. |
Contract 2 |
MM12 – Screen Planting |
Not applicable during the reporting period. |
NA |
MM13 – Roadside Planting |
Not applicable during the reporting period. |
NA |
MM14 – Aesthetic Design of Built Development |
Not applicable during the reporting period. |
NA |
MM15 – Maximise Greening on Structures |
Not applicable during the reporting period. |
NA |
MM16 – Noise Barrier Design |
Not applicable during the reporting period. |
NA |
MM18 – Landscaping on Slopes |
Not applicable during the reporting period. |
NA |
MM20 – Lighting Control |
The implementation of mitigation measures was checked by ET during weekly site inspection. Implementation of the measures by Contractors was observed. |
All works contracts |
Table 2.10
Monitoring Programme for Landscape and Visual
Stage |
Monitoring Task |
Monitoring Report |
Form of Approval |
Frequency |
Design |
Monitoring of design works against the recommendations of the landscape and visual impact assessments within the EIA should be undertaken by the Engineer and Landscape Architect, to ensure that they fulfil the intentions of the mitigation measures. Any changes to the design, including design changes on site should also be checked |
Report by CEDD / ER confirming that the design conforms to requirements of EP. |
Approval by Project Proponent |
At completion of design stage |
Construction |
Monitoring of the contractor’s operations during the construction period. |
Report on Contractor's compliance by ET |
Counter-signature of report by IEC |
Monthly |
Establishment Works |
Monitoring of the planting works during the 24-months Establishment Period after completion of the construction works. |
Report on Contractor's compliance by ET |
Counter-signature of report by IEC |
Bi-monthly |
A summary of the Environmental
Mitigation Implementation Schedule is presented in Annex B. The necessary
mitigation measures were implemented properly for the Project.
There was no notification of
summons or prosecution recorded in the reporting period.
One (1)
environmental complaint related to Contract 3. Investigation was conducted
for the environmental complaint in accordance with the complaint handling
process as stated in the Complaint Management Plan. Environmental
complaints in the reporting period are summarized below.
|
Complaint(s) |
Investigation/Follow up action(s) |
1 |
Environmental complaint related to Contract 3 regarding dust over the construction site near Yu Nga Court and Ying Tung Estate was received on 18 October 2024. |
According to the Contractor and ET’s regular inspection, water truck was deployed for hourly watering of works areas and haul roads on every working day starting at 08:00 except in rainy hours. The Contractor has also installed automatic sprinklers at work area near residential buildings for dust suppression. Water spraying by manpower was also carried out during excavation works. |
Statistics on complaints, notifications of summons, successful
prosecutions are summarised in Annex K.
Works to be undertaken in the next monitoring period of
November 2024 are summarized in Table 3.1 below, together with the key
issues and the key mitigation measures:
Table 3.1
Major Activities for the Next Reporting Period
Activities |
Key Issues |
Key Mitigation Measures |
Contract No. NL/2017/03 - Tung Chung New Town Extension – Reclamation and Advance Works (Contract 1) |
||
Land-based Works |
||
• Removal of siltation at IORC
|
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management · Potential surface runoff · Noise from plant operation during normal working hours or restricted hours · Dust emission during storage and transfer of sand/ sorted public fill |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management · Strictly follow requirement under CNP for the use of PMEs and works within restricted period · Use of acoustic mat and other noise mitigation measures when necessary · Regular maintenance of engines and mechanical equipment |
Contract No. NL/2020/02 - Tung Chung New Town Extension – Salt Water Supply System (Contract 2) |
||
Land-based Works |
||
· Construction of pumping station at Portion 6 · Construction of Intake Culvert at Portion 6 · Construction of service reservoir, TMF mainlaying at Portion 3 · Construction of HDD works at Portion 3 · Watermain laying works at Portion 3 along Man Tung Road, Tung Chung Road and Tung Chung Waterfront Road · Construction of T-Junction in Yi Tung Road at Portion 5
|
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management · Tree protection |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management · Retain and protect all existing trees and vegetation within the study area which are not directly affected by the works |
Contract No. NL/2020/03 - Tung Chung New Town Extension – Major Infrastructure Works in Tung Chung East (Contract 3) |
||
Land-based Works |
||
· Excavation and ELS works at Portion 104 · Excavation and ELS works at CUT no.1, 2, 3, 4 and supporting building · Construction works for CUT no. 1 structure · Back-filling works for CUT 2 · Construction works and furniture installation of PM office at WA9 · Construction works of Contractor office at WA6 · Drainage, Sewerage and watermain works at Road L4, L3, L5 and Portion 16 · DCS works at Road L4 and L3. · Pipe laying works for twin rising mains/ watermain laying at Man Tung Road · Preparation and pipe jacking works at Ying Tung Road · Pipe jacking works at Yi Tung Road · Foundation and backfilling works for noise barrier at Portion 11 · Road and drainage works in Road P1 · Road widening works at Ying Hei Road · Road D4, Road L7, ELS installation
|
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management |
Contract No. NL/2020/07 - Tung Chung New Town Extension – Tai Ho Interchange (Contract 7) |
||
Land-based Works |
||
· Open cut excavation, backfilling and pipe laying for rising main and watermain at Portion 146-1 to 146-5 · Pak Mong Bridge insitu construction of abutment, diaphragm and cable trough · Trench excavation and pipe laying works at Portions 32 (Sham Shui Kok Drive) · Trench excavation and pipe laying works at Portion 32 (Access Road adjacent to MTRC Siu Ho Wan Depot) · Establishment of pipe jacking works at Portion 33 · Horizontal grouting at Receiving pit at Portion 32 · RC construction of Retaining Wall FR1 at Portion 31 · Pak Mong Subway Extension Phase 2 - Demolition of existing Subway and Sheetpiling for ELS · Steel tower installation at Casting Yard A1 and A2 · Formwork and rebar fixing for Bridge A1 and A2 · ELS at A1a, A1b · RC construction for A1a, A1b, A2a, A2b Abutment · RC for RW-R2 and RW-R4 at Portion 146-2 to 146-4 · RC construction at RW-R7 at Portion 31 · RC works at Wall E · Mini-piles at Wall D · Bored piles at Bridge C at Portion 146-12 · U channel and chain link fence construction at Portion 147-1 and 147-2 · Sign gantry ELS, RC works, crossroad ducts, temporary lighting arrangement and removal of central divider along NLH fast lane · Drainages works at 146-4, 146-6 and 146-7 · Site clearance and tidiness
|
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management · Tree protection |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management · Retain and protect all existing trees and vegetation within the study area which are not directly affected by the works |
The ET will keep track on the construction works to confirm
compliance of environmental requirements and the proper implementation of all
necessary mitigation measures. The ET will also recommend to the
Contractors about the environmental toolbox topics on the abovementioned key
issues for the next reporting period.
The tentative schedules for environmental monitoring in
November 2024 are provided in Annex
L.
This EM&A Report presents the
findings of the EM&A activities undertaken for the TCE Project during the
period from 1 to 31 October 2024 in accordance with the Updated EM&A Manual
and the requirements of the Environmental Permit (EP-519/2016).
Air quality (1-hour TSP), noise,
and in-situ preserved plant species of conservation importance monitoring were
carried out in the reporting period.
The monitoring results for air
quality monitoring (1-hour TSP) complied with the Action/ Limit levels in the
reporting period.
No exceedance of Action/Limit
Level was recorded for construction noise monitoring in the reporting
period.
Water quality monitoring was
suspended in the reporting period.
Mangrove eco-shoreline, rocky
eco-shoreline and vertical eco-shoreline were completed. No eco-shoreline
monitoring was scheduled during the reporting period.
No post-construction soft shore
ecological monitoring at Tung Chung Bay and Tai Ho Wan was conducted during the
reporting period.
No compensation woodland
monitoring was carried out in the reporting month.
Monitoring of the in-situ
preserved plant species of conservation importance was carried out in the
reporting period.
No monitoring of the transplanted
plant species of conservation importance was carried out in the reporting
period.
Environmental site inspections
were carried out during the reporting period. Recommendations on remedial
actions were given to the Contractors for the deficiencies identified during
the site inspections.
There were no notification of
summons or prosecution recorded in the reporting period. One (1)
environmental complaint related to Contract 3. Investigation was
conducted for the environmental complaint in accordance with the complaint
handling process as stated in the Complaint Management Plan.
The ET will keep track on the
construction works to confirm compliance of environmental requirements and the
proper implementation of all necessary mitigation measures.
([1])
ERM (2018a). Updated Environmental Monitoring and Audit Manual for
Tung Chung New Town Extension. Deposited to EPD under EP-519/2016
([2])
Arup (2015). Environmental Impact Assessment Report for Tung Chung
New Town Extension. Deposited to EPD under Register No. AEIAR-196/2016